MANILA, Philippines – An initial
evaluation by a special team of the Commission on Audit (COA) on
the controversial Makati City Hall 2 parking building showed a “very
significant” discrepancy of P124 million between the contract cost
and COA’s “evaluated cost.”
The five-phase parking
building project has been the subject of an investigation by the Senate
body amid allegations that it was overpriced.
Alexander Juliano, director of
COA’s fraud office audit, read before the blue ribbon sub-committee,
an eight-page preliminary report by the team, which was later furnished to
reporters.
The report showed that COA’s evaluated
cost for the first four phases of the project was P2.126
billion while the actual contract cost was P2.011 billion for a
difference of about P124.6 million.
It made no mention of its
comparison for Phase V of the project.
“From the tables above, it can be
gleaned that for Phases 1 to IV alone, there was a total variance between
the ABC and the COA Evaluated Cost amounting to P126, 098, 558 while the
Contract Cost vis-a-vis the COA Evaluated Cost had a total variance
of P124, 676, 158. These amounts are very significant,” it said.
“Further, the percentages of variances
for Phases III and IV are within the borderline of the10 percent allowable
variance. The materiality of the variance (contract price is above
COA evaluated cost) deserves a deeper analyses and evaluation,” it
added.
For all five phases of the
project, the report showed that the city government had
disbursed an aggregated amount of P2, 367, 679.633.95 as of
Dec. 31, 2013, including the preliminary services amounting to P11, 974,
900 and P75,614, 953.01 for the Building Management System.
The following
were the amounts spent by the city government for every
phase of the project:
Phase
1
P386, 998, 154.20
Phase 2
P499 , 357, 003.73
Phase 3
P599,994, 021.05
Phase 4
P649, 934, 440.96
Phase 5
P443, 806, 161.0
Among the findings of
the special team was that the project was “implemented with undue
haste as there were no construction plans yet when it was
bidded out and awarded to Hilmarc’s Construction Corp.”
“A perusal of the records wills
show that Phase 1 was implemented with undue haste,” it said.
“Firstly, there was only a gap of one
month from the passage of the appropriation ordinance on Nov. 8, 2007 when
the IAEB for the project was advertised on Dec. 6, 2007.” IAEB
stands for Invitation to Apply and Submit Eligibility to Bid.
“While the swiftness of the
action taken by the government may be considered as efficiency, the same
could also be considered as a red flag because this project with such a huge
budget will surely require a careful conceptualization
and planning,” said the report.
It also appears, it said, that the
negotiated procurement adopted by the BAC on the contract of architectural
and engineering services “was improper because none of the conditions
laid down under Section 53 of the Implementing Rules and Regulations
of R.A No. 9184 was present such as failed biddings, emergency cases, takeover
of contracts, adjacent or contiguous projects, agency-to agency, highly
technical consultants and defines co-operation agreement.”
BAC is bids and awards committee.
The report further noted that that
the city started the procurement process for Phase III on Nov. 27,
2009 even if there was no appropriation yet at that time.
“The covering appropriation
ordinance was only enacted on September 14, 2010,” it pointed out.
Source: www.inquirer.net
No comments:
Post a Comment